Project Update - WSC07-1221-C / Britain 4


Project Number Manufacturer Model Cylinders Driver Stages Status Est. Delivery
WSC07-1221-C LeROI LG-30 N/A 250 HP Electric N/A In-Process Dec. 15, 2007

Build Status as of 11/1/07;

Compressor: LG-30 LeRoi screw compressor frame received at shop / Nowata, OK

Cooler: Fabrication of cooler should be completed by 11/17/2007

Control Panel:
Received at Shop / Nowata, OK

Motor Soft Start: Received at Shop / Nowata, OK.

Motor: Received at Shop / Nowata, OK.

Concrete Filled Skid: Fabrication completed / concrete poured and set up - Ready for top assembly.

Pre-Separator: Received in Nowata on 11/1/2007

Inlet Separator: Received in Nowata on 11/1/2007


Assembly: Estimated start date 11/2/2007, after receipt of separators

Payment History;

Billed on: 09/20/2007


Payment received on: 10/09/2007


Photos



Murphy Centurion N/C Control Panel



ABB Motor Soft Start w/ Fan Drive Start



LeROI Code Oil-Gas Separator



250 HP 1750 RPM 480v-3P-60Hz TEFC Drive Motor



LeROI LG-30 Rotary Screw Frame with Unloaders



Aluminum Spin-Cannister Oil Filtration System



Skid Assembly with Steel Deck - Concrete Filled - 4 Point Loading and/or Tail Board Load


[ Inquiry Form ]
[ Horsepower Sizing Chart ]


Project last Updated November 1, 2007


Home | Reciprocating | Rotary Screw | Turbine | Process Equipment | Inquiry


Copyright © 1997-2007 Wellsite Compressor & Equipment Co., LLC - All Rights Reserved
Photographs Copyright © 1997-2007 Wellsite Compressor & Equipment Co., LLC - All Rights Reserved